Structural Issues: Signs of corrosion at the node junctions, bolt penetrations and I-beam surface
Scope of Work:
- Structural Improvements
- Industrial Coatings
- Concrete Repairs
Benefits of Rope Access:
- Eliminates need for unsightly & expensive scaffolding systems
- Allows the bridge to be reopened after work hours
- Minimal disturbance to the bridge
Job facts:
- A six week job completed on time & on budget
- Work expected to add fourteen years life to the bridge
- Advanced rigging and encapsulation techniques
- Substantial cost savings with minimal disruption to the bridge
Quality, Safety & Environment:
- PCCP (Painting Contractors Certification Program)
- Quality control & ITP’s (Inspection and Test Plan)
- NACE inspection
- Site inductions & daily safety briefs
- Took approved safety precautions for the presence of lead systems in place to protect the Yarra River and surrounding park lands with an effective environmental plan
- Safely executed procedures for working with lead based paint
- Custom safety and environmental catchment frame underneath workers